“A lot of the work that I do is historic-the maximum sentences change at different points of time. It's really complicated and people get it wrong all the time. That's when having a timeline is really useful.”
1 High PavementAccess all documents on Dispute escalation procedure
Pevensey Coastal Defence Ltd v Environment Agency [2024] EWHC 1435 (TCC)) What are the practical implications of this case? This dispute is highly fact‑sensitive, largely focused on construing terms in a particular PFI contract. Nonetheless, some issues of broader interest arise from the circumstances prompting the claim and the treatment of clauses addressing adverse weather — here, the escalation in storm activity along the Sussex coast — within a PFI arrangement that began in 2000 and ends in 2025. Parties might scrutinise the Change Control Schedule wording in the judgment and decide whether to seek the same outcome recognised here (namely, that costs could be recoverable where there has been a material rise in storm incidents/adverse weather). In essence, the issue was whether the Change Control Schedule allowed recovery of extra costs from a material uptick in storm events. Similar PFI parties should review that drafting. What was the background? Pevensey Coastal Defence Limited (PCDL) and the Environment Agency (EA) entered into a PFI contract dated...
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z D&B See Design and build beneath. DBO See Design, build and operate beneath. Date for completion/completion date Means the date stated therein in the building contract (typically within the contract particulars/contract data) by which the contractor must finish the works—ie the point by which practical completion is to be achieved (see Practice Note: What is practical completion?). This completion date may change over the course of the project, for instance where the contractor receives an extension of time. Should the works not be completed by the completion date, the contractor is liable to the employer for liquidated damages (where the contract so provides) or, failing that, general damages for delay in completion (arising from breach of contract thereunder). Date for possession The date set out in the building contract on which the employer gives...
Many contracts include provisions on resolving disputes. At times these are simple terms stipulating litigation or possibly arbitration, sometimes also spelling out jurisdiction and the governing law. Yet a clause can instead prescribe other routes of alternative dispute resolution (ADR) to be pursued should a dispute arise, offering an alternative to litigation or arbitration. Such provisions are often labelled ADR clauses. Parties have a number of options open to them (see below), and it is vital to appreciate the consequences of the drafting choices you make. This Practice Note reviews several clause formulations and evaluates the issues that may arise in relation to each category. The types of dispute resolution clause considered in this Practice Note are: litigation only clauses mediation clauses multi-tier clauses (escalation clauses) hybrid clauses carve-out clauses For guidance on the principal questions around the enforceability of dispute resolution clauses and on challenging jurisdiction (including applying to stay proceedings) where proceedings are commenced in breach of...
This Practice Note offers guidance on tiered dispute resolution clauses (also known as multi-step, escalation, ADR-first and stepped procedure clauses) in construction contracts, and examines the legal and practical issues they raise, including what happens when parties disregard them. It also provides practical tips for drafting or amending these clauses so they operate effectively for the parties and the projects they support. What are tiered dispute resolution clauses? Tiered dispute resolution clauses are commonplace in construction contracts. They require contracting parties to move through a series of alternative dispute resolution (ADR) stages before any unresolved dispute is referred to a final forum, typically litigation or arbitration. These stages can be mandatory, preventing the parties from advancing to the next or final step in the process until the preceding stage has been completed. Why use a tiered dispute resolution clause? Parties to construction contracts adopt tiered dispute resolution clauses to establish a structure within which they can try to resolve disputes without resorting to litigation or arbitration,...
This Agreement is entered into on [ insert date ] Parties [ insert name ], a company incorporated in [ England and Wales ] with registered number [ insert registered number ], whose registered office is at [ insert address ] (Supplier); and [ insert name ], a company incorporated in [ England and Wales ] with registered number [ insert registered number ], whose registered office is at [ insert address ] (MVNO). Each of the Supplier and the MVNO is a party and, together, the Supplier and the MVNO are the parties. Background The Supplier operates a mobile network within the Territory. The MVNO functions as a mobile virtual network operator in the Territory. The Supplier has agreed to supply wholesale mobile electronic communications services to the MVNO for onward sale [ on a pre-pay basis OR on a post-pay basis OR on a pre-pay and post-pay basis ] in the Territory, in accordance...