“What I spend on my yearly subscription, equals to a day's billable hours for me not to mention time efficiency and peace of mind.”
Jai SternAccess all documents on LADs
This Checklist This Checklist outlines key points to consider when preparing or negotiating liquidated damages (LADs) provisions in a building contract, with a particular emphasis on LADs for late completion. It offers practical pointers and guidance designed to help ultimately ensure that LADs provisions in a building contract are properly enforceable...
On 17 April 2024, JCT released the 2024 versions of its Design and Build (DB) Contract and the Design and Build Sub-Contract (DBSub), together with the accompanying guides. The JCT Design and Build forms are aimed at projects where the contractor is responsible for completing the design as well as delivering the works. The JCT DB Sub-Contracts are intended for use where the main agreement is the JCT DB, and may apply either when the sub-contract package is fully designed or when the sub-contractor must design part or all of the works. In this piece, we explore some of the principal updates in the 2024 JCT DB documents compared with the 2016 suite, concentrating on JCT DB 2024 (ie the main contract). Reference copies of JCT DB 2024 and JCT DBSub 2024, and their companion guides, can be found on Lexis+ Construction under the sub-topic ‘JCT contracts 2024’ within the main topic ‘Standard form construction contracts’. They are also available via Practice Note: JCT contracts 2024—reference copies. What are...
On 15 May 2024, the Joint Contracts Tribunal (JCT) released its 2024 versions of the Minor Works Building Contract (MW), the Minor Works Building Contract with contractor’s design (MWD), the Minor Works Sub-Contract with sub-contractor’s design (MWSub/D), the Short Form of Sub-Contract (ShortSub) and the Sub-subcontract (SubSub) 2024. This follows the 17 April 2024 publication of the Design and Build Contract and the Design and Build Sub-Contract Agreement and Conditions, together with the related guides (see News Analysis: The JCT Design and Build Contract 2024—what’s changed?). These forms sit alongside the April releases and guides. The JCT MW and MWD suites are geared for schemes of relatively modest value where the Contractor must perform the construction works, and, for MWD, also undertake a defined element of the design responsibilities. MW covers the works, whilst MWD includes a contractor-designed portion carried out by the Contractor. The JCT MWSub/D is designed for projects where the main contract adopts the JCT MWD form, and sets out obligations concerning designs delivered by the sub-contractor...
Energy Works (Hull) Ltd v MW High Tech Projects UK Ltd and another [2022] EWHC 3275 (TCC) What are the practical implications of this case? The comprehensive judgment of the Honourable Mr Justice Pepperall sets out the practical hazards and challenges frequently faced on energy and infrastructure schemes, particularly where advanced technology intensifies complexities in design and construction. It further highlights the significance of a contractor’s reporting duties, within a contractual framework that did not restrict liability for wilful defaults, including the deliberate misreporting of progress. This ruling will be of clear interest to practitioners, construction professionals and other stakeholders working across the construction, infrastructure and energy sectors. The court also provided useful guidance and clarification on several broader legal issues relevant to disputes arising in construction, infrastructure and energy projects. First, the court confirmed that, in the absence of express contractual or statutory provisions, a contractor has no general right to suspend works or to address an employer’s breach as it chooses; the...
Even with advanced procurement techniques, scheduling tools and project management applications, construction schemes can still run late and overrun. Any slippage triggers extra cost. This Practice Note explores the delay damages regime designed to safeguard an employer if delay occurs, highlighting the relevant FIDIC clauses and other standard form contracts used in the energy sector that address delay damages. See also Practice Notes: Delay and disruption in construction projects and Time and money claims. The importance of time in energy projects Construction and energy contracts devote substantial attention to time, particularly setting a completion date. Most building contracts provide for delay damages (also termed liquidated damages or liquidated and ascertained damages (LADs)). The core concept is that, on specified breaches by the contractor—commonly failure to complete on time, but potentially performance shortfalls—agreed damages become payable to the employer. Fixing those sums before contract award seeks to avoid protracted and costly proceedings required to demonstrate actual loss...
This Practice Note This Practice Note considers the principal factors a party to a construction contract should address when preparing the quantum elements of a claim. It covers routine contractual claims (for example, loss and expense), as well as scenarios where the dispute stems from breach of contract or negligence, i.e. a claim for damages. It also examines frequent categories of recoverable loss, including: damages relating to defects claims future losses wasted management time loss of a chance third party settlement sums Beyond establishing whether a loss is recoverable and its value, additional quantum issues may include whether to advance a ‘global claim’, mitigation and betterment considerations, contributory negligence, and any contractual limits or exclusions. On the issue of loss within a dispute, the claimant bears the burden of proving both the fact of the loss and the amount claimed. For a fuller review of key and/or recent authorities concerning common heads of loss in construction disputes, such...
CASE HUB NOTE—appeal lodged before the General Court in Case T-84/22 ARCHIVED — this archive reflects the position as at the 2 December 2021 decision and is no longer maintained. For more, see the timeline, commentary, and related cases. Case facts Outline European Commission Article 101 TFEU investigation into three cartels in the Spot Foreign Exchange market for 11 markets (AT.40135). The cartels featured the exchange of confidential information and, at times, the coordination of trading strategies. Latest development On 2 December 2021, the Commission adopted a second infringement decision after Barclays, RBS and HSBC settled with the Commission and acknowledged participation in a third cartel (the Commission’s 2021 decision). Fines totalling €261m were issued. Under the ordinary procedure, the Commission also imposed fines of €83m on Credit Suisse. For the ‘Sterling Lads’ cartel, the penalties were: UBS — €0 (immunity granted) Barclays — €54,348,000 (including a 30% reduction for leniency and a 10% reduction for settling) RBS —...
IN THE MATTER OF the Housing Grants, Construction and Regeneration Act 1996 AND IN THE MATTER OF an adjudication before [ Name of Adjudicator ] Between [ Name of party 1 ], the Referring Party, and [ Name of party 2 ], the Responding Party RESPONSE Introduction This document is the Responding Party’s response to the Referring Party’s Referral Notice, served on [ date ] (the Referral). A supporting bundle accompanies this Response, comprising the following materials: chronology of relevant events at tab [ insert ] (Tab [ insert ]) [ insert ] at tab [ insert ] (Tab [ insert ]) [ insert ] at tab [ insert ] (Tab [ insert ]) References within this Response to the documents and materials appended to the Notice of Adjudication and the Referral follow the terminology and document labels adopted by the Referring Party. This Response focuses on the...