Payment Notice meaning

/ˈpeɪm(ə)nt/ /ˈnəʊtɪs/
What does Payment Notice mean?
In construction payment practice, a payment notice is the document that states the sum due for a particular payment and how that figure has been calculated. In England and Wales and Scotland it is a statutory notice under the Housing Grants, Construction and Regeneration Act 1996, section 110A (as amended). A broadly equivalent regime applies in Northern Ireland under the Construction Contracts (Northern Ireland) Order 1997 (as amended). It must specify the “notified sum” and the basis of calculation, and is usually issued by the payer or a specified person (for example, a contract administrator) no later than five days after the payment due date. Most standard form construction contracts allocate this obligation to the payer (or specified person). If no payment notice is given, the payee may serve a default notice that becomes the operative payment notice. The payment notice fixes the notified sum and starts the period for any pay less notice. Absent a valid pay less notice, the payer must pay the notified sum by the final date for payment, with failures commonly pursued by adjudication. In Ireland, the comparable concept is a “payment claim notice” under the Construction Contracts Act 2013 (served by the payee), with a “payment...
Speed up all aspects of your legal work with tools that help you to work faster and smarter. Win cases, close deals and grow your business–all whilst saving time and reducing risk.

View the related Checklists about Payment Notice

CHECKLISTS
Suspending performance for non‑payment under the HGCRA 1996: section 112 rights, notice requirements, scope, costs, completion impact and pre‑2011 differences

This Checklist reviews the entitlement to suspend under the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996), and the matters that ought to be carefully considered before any party opts to suspend carrying out its obligations and duties under a construction contract. Is there a general common law right to suspend a contract? No. At common law, a party to a contract has no general right to pause or withhold ongoing performance of contractual duties when the other party is in breach, unless the breach is sufficiently serious to constitute a ‘repudiatory breach’, thereby permitting the innocent party to rescind or bring the contract to an end (see Practice Notes: Termination of a construction contract—Common law termination and Repudiation of contract). How does the right to suspend arise in a construction contract?...

Read More Right Arrow
CHECKLISTS
Probate caveats under the NCPR 1987: entry, extension, warning, appearance, withdrawal, fees, time limits and forms—procedural guide for practitioners (England and Wales)

Caveat is entered Non-Contentious Probate Rules 1987 (NCPR 1987), SI 1987/2024 (as amended) Apply for a caveat online or via Form PA8A (see the forms tab within the Probate actions subtopic) — NCPR 1987, SI 1987/2024, r 44(2). The caveator lodges the caveat at the Principal Registry of the Family Division or at a district probate registry by post or electronically — NCPR 1987, SI 1987/2024, r 44. Fee: £3; if submitted electronically, payment must also be electronic — NCPR 1987, SI 1987/2024, r 44. The deceased’s name is recorded in the index of caveats — NCPR 1987, SI 1987/2024, r 44(4). Unless otherwise provided, the caveat endures for six months from the date of entry — NCPR 1987, SI 1987/2024, r 44(3)(a). The index of caveats is checked — NCPR 1987, SI 1987/2024, r 44(4). On receiving an application for a grant at the registry of filing or notice of an application made elsewhere, the district judge or registrar...

Read More Right Arrow
CHECKLISTS
Real estate finance: checklist for perfecting security—Companies House, HM Land Registry, unregistered land, notices and assignments (England and Wales)

This Checklist This Checklist explains the actions property solicitors must take to perfect security in a real estate finance transaction. Real estate finance lenders will typically seek a comprehensive security package over all assets connected with the real estate. A real estate solicitor within a multi-disciplinary team will commonly arrange or contribute to the following securities and documentation: security over the land, rental income, insurance proceeds, development and construction, and contractual rights reviewing the management agreement and negotiating a duty of care agreement (although in a multi-disciplinary team, this is sometimes handled by the banking and finance lawyer) dealing with completion undertakings and post-completion registration of the legal charge at Companies House and HM Land Registry, as well as giving third party notices regarding rent payment, notice of charge and, where necessary, assignment of contractual rights or warranties See Practice Notes: Security in real estate finance transactions, Taking security over land and Taking security over unregistered land and Taking and perfecting...

Read More Right Arrow

View the related Flowcharts about Payment Notice

FLOWCHARTS
Archived: Commercial Rent (Coronavirus) Act 2022 arbitration: eligibility, notices, hearings, awards and moratorium end; scheme closed to new references (England and Wales)

This Flowchart This Flowchart supports your decision on whether a data protection impact assessment (DPIA) is necessary when initiating a new project that involves personal data from the outset, helping you decide effectively. It sets out: three scenarios in which a DPIA is mandatory under Article 35(3) of Assimilated Regulation (EU) 2016/679, UK General Data Protection Regulation (UK GDPR); and ten further processing activities for which the Information Commissioner’s Office (ICO) requires a DPIA to be carried out Where a DPIA is not needed, you should think about using a simpler form of review, which we call a privacy impact assessment (PIA) instead. The Flowchart enables you to determine which assessment—DPIA or PIA—best fits your project in practice. For additional guidance on DPIAs and PIAs, see Practice Note: How to complete a data protection impact assessment—DPIA...

Read More Right Arrow

View the related News about Payment Notice

NEWS
Construction law update: TCC Sunday deadline ruling, HRB gateway updates, PAP reform, UKSC digital portal, investment treaty award upheld, CIS change for traffic management, SBCC 2025 pricing, sector news

In this issue: Contract law Building safety Litigation Arbitration Tax for construction lawyers Standard form contracts Construction industry news Daily and weekly news alerts New and updated content Construction trackers Contract law Employer deemed out of time in issuing a notification on the Monday after a Sunday deadline (My Contracts v 74 Hamilton Terrace) In My Contracts Ltd v 74 Hamilton Terrace Freehold Ltd [2024] EWHC 2896 (TCC), the TCC issued a declaration at the contractor’s request concerning the construction of a clause that imposed a deadline for the employer to notify costs for which the contractor was responsible. The court concluded the employer missed the deadline by serving the notice on the Monday immediately after the final day for service, which had fallen on a Sunday. Central to the decision was that the clause made no provision for the period to be calculated by reference to ‘Business Days’. See News Analysis: Employer...

Read More Right Arrow
NEWS
HGCRA 1996 adjudication: 'true value' and 'smash and grab' constitute a single dispute; adjudicator may decide both in one reference—Bellway Homes v Surgo (TCC, England and Wales)

Bellway Homes Limited v Surgo Construction Limited [2024] EWHC 10 (TCC) What are the practical implications of this case? In adjudications governed by the Housing Grants, Construction and Regeneration Act 1996 (HGCRA 1996), a party is permitted to place only one dispute before the adjudicator (HGCRA 1996, s 108(1)). Where more than one dispute is advanced, the adjudicator has no jurisdiction to proceed (Fastrack v Morrison). This decision is the first to address whether a payee’s interim payment claim that proceeds on two alternative footings—(i) the true valuation of the works and/or (ii) entitlement to the sum applied for because no valid payment or pay less notice was served (often termed a ‘smash and grab’ claim)—should be treated as a single dispute. The court concluded that it is one dispute, with the consequence that an adjudicator has jurisdiction to consider both bases within the same reference. The outcome will be of real importance to parties engaged in interim payment contests, as it confirms that valuation and notice-default arguments...

Read More Right Arrow
NEWS
HGCRA 1996 adjudication notices: TCC backs common-sense approach; lesser sums and due-date errors do not invalidate applications (1st Formations v LAPP) (England and Wales)

1st Formations Ltd v Lapp Industries Ltd [2025] EWHC 1526 (TCC) What are the practical implications of this case? This decision underscores that the courts will adopt a common-sense, pragmatic approach to the content of a payee’s notice under the HGCRA 1996 and Part II of the Scheme for Construction Contracts (the Scheme), resisting unduly narrow readings. So long as the notice makes sufficiently clear what sum is sought and the footing for the claim, the court will not seek to interfere or hunt for defects that might render the notice void or ineffectual. Here, the payee’s documents were plainly recognisable as an interim application; they identified the amount asserted as due and the basis upon which that figure had been worked out. The TCC further confirmed that a payment notice is not invalid merely because it asks for a figure below the amount stated as due. If a payment notice includes an incorrect due date, that is an issue for the other party to pick up in...

Read More Right Arrow

View the related Practice Notes about Payment Notice

PRACTICE NOTES
Furloughed employees: calculating a week’s pay for redundancy, notice, unfair dismissal awards and related entitlements under the 2020 Week’s Pay Amendment Regulations [Archived]

ARCHIVED: This Practice Note is archived and not being maintained. It reviews the Employment Rights Act 1996 (Coronavirus, Calculation of a Week’s Pay) Regulations 2020 (Week’s Pay Amendment Regs 2020), SI 2020/814, which ensure that employees furloughed under the Coronavirus Job Retention Scheme (CJRS) for any period ending on or before 30 September 2021 receive statutory redundancy pay, statutory notice pay and other entitlements by reference to their usual earnings rather than the reduced furlough rate. For details on the Coronavirus Job Retention Scheme (CJRS), extended to 30 September 2021, see Practice Note: Coronavirus Job Retention Scheme (extended version 1 May to 30 September 2021) [Archived]. For general guidance on working out a week’s pay under sections 221–224 of the Employment Rights Act 1996 (ERA 1996), see Practice Note: Calculating a week’s pay. The Employment Rights Act 1996 (Coronavirus, Calculation of a Week’s Pay) Regulations 2020 (Week’s Pay Amendment Regs 2020), SI 2020/814, which took effect on 31 July 2020, prescribe how a week’s pay is to...

Read More Right Arrow
PRACTICE NOTES
Statutory Adoption Pay in Great Britain: Eligibility, notice and evidence, calculation, duration, liability (incl. multiple employers), disrupted placements, recoupment, and interaction with contractual pay, surrogacy and overseas adoptions

This Practice Note considers statutory adoption pay (SAP) and contractual adoption payments. It also examines eligibility criteria, the meaning of employed earner, the duration of entitlement, notice obligations, the evidence required, the length of time SAP is payable, rates of pay, and liability, including where an individual has more than one employer. It addresses outcomes where a child dies or a placement breaks down, circumstances in which SAP is not due, record-keeping duties, and how recoupment operates. Finally, it explores how contractual sick pay interacts with SAP, adoptions from outside the UK, and contracting out. A parent taking adoption leave (see Practice Note: Adoption leave) may qualify for SAP for part of that leave. They may receive payment for time off to attend adoption appointments (see Practice Note: Time off work for adoption appointments). Where a child is placed for adoption, the adopter and a second person—who must be the adopter’s spouse, civil partner, or partner—may, if they choose, share up to 37 of the 39 weeks of pay...

Read More Right Arrow
PRACTICE NOTES
Practitioner’s guide to lodging immigration appeals in the First-tier Tribunal (IAC), UK: deadlines, MyHMCTS, forms, fees and remissions, urgent appeals, anonymity and Rule 22 non-acceptance

Practice Note This Practice Note sets out the procedure for lodging an appeal before the First-tier Tribunal in the Immigration and Asylum Chamber. For an overview of the principal stages involved in a standard First-tier Tribunal appeal, refer to Practice Note: Procedure in the First-tier Tribunal (IAC). For the procedural sequence and further practical considerations when preparing a First-tier Tribunal appeal, see Practice Note: Preparing for an immigration appeal to the First-tier Tribunal (IAC)...

Read More Right Arrow

View the related Precedents about Payment Notice

PRECEDENTS
Board minutes precedent: approving or recommending an interim, final or special cash dividend by a private company limited by shares (Companies Act 2006)

Company registration number: [ insert company number ] [ insert company name ] [ LIMITED OR LTD ] Minutes for a meeting of the board of directors (the Meeting) of [ insert company name ] [ Limited OR Ltd ] (the Company) Held at [ insert place of meeting ] Held on [ insert day, month and year of meeting ] at [ insert time of meeting ] [ am OR pm ] Present: [ Insert names of directors attending, in person or by any remote method (unless such methods are expressly excluded by the company’s articles of association) ] [ by [ insert means of attendance for each director joining remotely ] ] [ In attendance: ] [ [ Insert name of any person present, in person or by any remote means, who does not count towards the quorum for the meeting (eg the company secretary, any legal advisers) ] ] [...

Read More Right Arrow
PRECEDENTS
Gazette notice template for payment out of capital to redeem shares under the Companies Act 2006, including inspection rights and five-week creditor objection period

Company number: [ insert number ] [ insert company name ] Limited (the Company) Payment out of capital for redemption of shares in the company In accordance with section 719 of the Companies Act 2006, the Company hereby gives notice that: On [ insert date ], the shareholders sanctioned a payment out of capital under section 716 of the Companies Act 2006 to enable the Company to redeem [ insert number of shares ] [ redeemable ] shares of £[ insert nominal amount ] each; The permissible capital payment, as defined by section 710 of the Companies Act 2006, for the relevant shares is £[ insert amount ]; The directors’ statement and the auditors’ report required by section 714 of the Companies Act 2006 in relation to the proposed out-of-capital payment are available for inspection at [ [ the registered office of the Company ] OR [ insert details of relevant address ] ] ; and Any creditor of the Company...

Read More Right Arrow
PRECEDENTS
Gazette notice template: payment out of capital for off-market share buyback by a private limited company (Companies Act 2006 Pt 18 Ch 5, s.719)

Company number: [ insert number ] [ insert company name ] limited (the Company) PURCHASE OF OWN SHARES OUT OF CAPITAL The Company gives notice under section 719 CA 2006 that: On [ insert date ], the Company passed a special resolution approving a payment out of capital under section 716 CA 2006 to purchase [ insert number ] [ insert class ] shares of [ insert nominal value ] each in its capital; The permissible capital payment (section 710 CA 2006) for the purchase is £[ insert amount ]; The directors’ statement and the auditor’s report required by section 714 CA 2006, regarding the proposed payment out of capital, are available for inspection at [ [ insert address of the Company’s registered office ] OR [ insert details of the Company’s alternative inspection location complying with CA 2006, ss 720, 1136 and the Companies (Company Records) Regulations 2008, SI 2008/3006, reg 3 ] ]; Any Company creditor may, within five weeks...

Read More Right Arrow

View the related Q&As about Payment Notice

Q&As
Commercial lease surrender: s.17 notice re guarantor no assignment?

Section 17 of the Landlord and Tenant (Covenants) Act 1995 (LT(C)A 1995) provides that: (1) This provision applies where a person (“the former tenant”) has, as a consequence of an assignment, ceased to be the tenant under a tenancy, but either: namely that (a) in the context of a new tenancy, has, under an authorised guarantee agreement, guaranteed his assignee’s performance of a tenant covenant of that tenancy under which any fixed charge is payable; or (b) in relation to any tenancy, still remains obliged by that covenant under that tenancy, notwithstanding assignment...

Read More Right Arrow
Q&As
CJRS furlough notice pay after agreed pay cut: SI 2020/814 or reduced rate?

Employment Rights Act 1996 (Coronavirus, Calculation of a Week’s Pay) Regulations 2020 (Week’s Pay Amendment Regs 2020), SI 2020/814 For broader guidance on SI 2020/814, see Practice Note: Coronavirus Job Retention Scheme—right to statutory redundancy and other termination payments [Archived]. This resource provides general context on the Employment Rights Act 1996 (Coronavirus, Calculation of a Week’s Pay) Regulations 2020 and their application... The Week’s Pay Amendment Regs 2020, SI 2020/814, prescribe how to determine a week’s pay for an employee who is, or has previously been, furloughed under the CJRS. The rules apply when calculating specified payments, including an employee’s entitlement to payment under section 88 or 89 of the Employment Rights Act 1996 (ERA 1996). In effect, the instrument clarifies the approach to weekly pay where furlough is relevant, ensuring the correct basis is used for these statutory sums linked to notice or other termination-related payments as identified under the ERA 1996...

Read More Right Arrow
Q&As
Ground rent arrears predating a leaseholder's freehold purchase

This Q&A raises the issue of the extent to which a person who takes an assignment of the reversion to a residential lease is able to recover rent which fell due before the date upon which it takes effect Upon serving the tenant with notice of assignment of the reversion, the assignee’s rights depend on when the residential lease was granted: Leases granted before 1 January 1996: under section 141 of the Law of Property Act 1925, the assignee is entitled to rent falling due in the future. In addition, as established in Re King, the assignee may pursue arrears that accrued before the assignment, and once the transfer takes effect, the outgoing landlord’s ability to recover those sums is lost. Leases granted on or after 1 January 1996: the Landlord and Tenant (Covenants) Act 1995 applies. By virtue of LT(C)A 1995, section 3(3)(b), an assignee of the reversion is entitled to rent which becomes payable after the assignment takes effect. In...

Read More Right Arrow