Powered by Lexis+®
Jurisdiction(s):
United Kingdom
CASE STUDY

“While we began looking at LexisNexis products primarily for cost saving, it quickly became more about customer service, ease of onboarding, ongoing training and breadth of resources available.”

Co-Op

Access all documents on TeCSA

TeCSA meaning

What does TeCSA mean?
TeCSA (the Technology and Construction Solicitors’ Association) is a professional association of solicitors specialising in construction, engineering and technology disputes, particularly matters before the Technology and Construction Court (TCC). It is not defined in legislation or case law; the term describes a widely recognised membership body within UK construction law practice. TeCSA is commonly named in construction contracts as an adjudicator nominating body for statutory adjudication under the Housing Grants, Construction and Regeneration Act 1996 (England and Wales). It also publishes adjudication rules adopted by parties and produces practical guidance for dispute resolution, including the TeCSA eDisclosure Protocol used in TCC litigation. TeCSA provides training, practitioner forums and liaison with the judiciary, and contributes to consultations on TCC procedure and pre‑action practice. Usage is broadly consistent across the UK. In Scotland and Northern Ireland (under the Construction Contracts (Scotland) Act 1997 and the Construction Contracts (Northern Ireland) Order 1997), parties may name TeCSA as a nominating body by agreement. In Ireland, TeCSA is recognised as a professional association but is not part of the statutory adjudication framework under the Construction Contracts Act 2013, where appointments are made via the ministerial panel. In practice, TeCSA’s involvement can influence the choice of adjudicator, procedural...
Speed up all aspects of your legal work with tools that help you to work faster and smarter. Win cases, close deals and grow your business–all whilst saving time and reducing risk.

View the related Practice Notes about TeCSA

PRACTICE NOTES
Construction and Engineering Disputes Pre-Action Protocol: Protocol Referee Procedure—Commencement, Appointment, Decisions, Non-compliance, Confidentiality and Costs

The second edition of the Pre-Action Protocol for Construction and Engineering Disputes (the Protocol) also introduces a formal mechanism allowing the parties to appoint a ‘protocol referee’ to direct how the Protocol should be conducted or to resolve allegations of non-compliance with it. The Protocol Referee Procedure (PRP) was devised and issued jointly by the Technology and Construction Solicitors’ Association (TeCSA) and the Technology and Construction Bar Association (TECBAR). A copy of the PRP is available here: The referee’s decision is binding upon the parties for the Protocol process—see The decision of the referee below. Until a decision is issued by the referee, however, the PRP does not affect the Protocol process; the time limits continue to run in accordance with the Protocol (PRP para 1.6). How does a party start the procedure? The procedure may only be used if both parties agree to it. In its letter of claim, the claimant should indicate whether it wants the PRP to apply, and the defendant should set out its...

Read More Right Arrow
PRACTICE NOTES
Construction law and procurement glossary—T: TCC, tendering, time bars, target cost, turnkey, Third Parties Act and FIDIC

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z Taking-Over Certificate The certificate issued by the Engineer under a FIDIC form (or by the Employer under the Silver Book) confirming that the Works, or a Section, have reached the level of completion required by the contract, together with the date this milestone was met; akin to a JCT certificate of practical completion. See Practice Notes: FIDIC contracts 2017—time and FIDIC contracts (pre-2017 editions)—time. Taking off The noting of measured dimensions extracted from drawings or schedules. This is the initial step in assembling bills of quantities. Target cost contract A form of cost reimbursable contract where the contractor is paid the actual cost of delivering the works, subject to a target cost agreed by the parties at project commencement. At completion, an agreed mechanism/formula determines whether there were savings or an overrun—the contractor then either shares any saving...

Read More Right Arrow